Turbines felled by explosives, Aug. 2026
Photo courtesy Dallas Laird / Your Wyoming Link
Chevron built the farm in 2009 under a PacifiCorp (Rocky Mountain Power) contract, then elected not to renew it in 2018. Output stopped entirely in December 2023.
16.5 MW
240 ft towers scrapped
2.5 years
idle before removal
2029
full reclamation target
In 2024, Chevron tried registering the farm in the West’s real-time Energy Imbalance Market — a workaround needing no long-term buyer — but PacifiCorp rejected it over an unresolved “telemetry issue” neither side ever explained. Chevron gave up: 4 of 11 turbines were sold intact for reuse elsewhere; the rest came down on-site by explosives and crane.
Source: Cowboy State Daily (Nov. 2024, Dec. 2024, Aug. 2026); Chevron decommissioning notices to Natrona County, Wyoming. Watch the demolition →